Completed Project
S.N. | Name of the Project | Date of Commencement | Actual Cost TK (In Million) | Date of Completion |
---|---|---|---|---|
1 | Bakhrabad-Chittagong Gas Transmission Pipeline | Jul,1980 | LC :1574.7 FC : 2031.4 Total 3606.1 | Jun, 1986 |
2 | South-east Bangladesh gas Distribution | Jul, 1983 | LC : 1366.6 FC : 802 Total 2168.6 | Jun, 1990 |
3 | Bakhrabad-Demra Gas Transmission Pipeline | Jul, 1984 | LC : 354 FC : 735.7 Total 1089.7 | Dec, 1987 |
4 | Gas Supply to 210 MW Raujan Power Station | Jul, 1991 | LC : 411.3 FC : 177.4 Total 588.7 | Jun, 1994 |
5 | Third Natural Gas Development (BGDCLComponent) | Jul, 1994 | LC : 218.7 FC : 147.3 Total 366 | Jun, 1998 |
6 | Gas supply project of Fulgazi, Porsuram and Chatkhil thana sadar. | Jul, 1995 | LC : 76.6 FC : 6.7 Total 83.3 | Jun, 1996 |
7 | Salda- Bakhrabad Gas Transmission Pipeline | Dec, 1996 | LC : 259.8 FC : 0 Total 259.8 | Mar, 1998 |
8 | Meghna-Bakhrabad Gas Transmission Pipeline | Dec, 1996 | LC : 48.1 FC : 92.5 Total 140.6 | Jun, 1998 |
9 | Grameen Gas Distribution (BGDCL Component) | Jan, 2000 | LC : 52.3 FC : 9.5 Total 61.8 | Jun, 2002 |
10 | Gas supply project of Chandpur 150 MW capacity thermal power station. | Dec, 2010 | LC : 367.5 FC : 427.6 Total 795.1 | June, 2013 |
11 | Pipeline construction project from Sundolpur gas field to Maijdi lateral line, Dagonbhuyan, Feni 8 inch dia 15 kilometer. | Nov, 2011 | LC : 89.4 FC : 0 Total 89.4 | March, 2012 |
12 | Lateral gas line project from Begumgonj gas field to Maijdi Setuvanga Bazar. | Oct, 2014 | LC : 57.5 FC : 0 Total 57.5 | June, 2015 |